Major new Data Centre project kicks off for Jones Engineering Group in Finland

Data Centre FinlandJones Engineering Group has just begun works on a new state of the art Data Centre in Finland. Working with a major multinational client at the cutting edge of their industry, our extensive experience in Data Centre’s made us an ideal candidate for this project.

Project Key Points

  • Over 12,000m of Pipe to be installed
  • Prefabrication of Pipe will be carried out in our Irish Workshops and delivered to site
  • Ductwork will measure nearly 4,600sqm upon completion
  • Expect to spend over 50,000 man-hours on the project
  • Data Centre includes both 10MW and 32MW infrastructure
  • Project completion is expected for December 2013

To learn more about this and more of our project experience, please visit: http://joneseng.com/projects/






Latest News

Are you ready? Walk In Interviews in London

Following the success of our Walk in Interviews on the 24th April we are delighted to announce a second date!

 

We are holding Walk in...

Company Announcement

We are delighted to announce that we have formed a new entity; Jones Engineering Group Acamar Bahrain Co. W.L.L.

The board and management are pictured...

Project Safety Role Model

Congratulations to our Electrical Team on the Tine site who were awarded Project Safety Role Model for their constant contribution to safety!

They excelled in...